Home > Installation > Program Preferences > General Tab

General Tab


Upon completion of the installation process and before attempting to use the system, you will need to complete the selection of your estimating preferences. This is accomplished by selecting the Program Preferences button from the top right of the opening screen. Each tab in the Program Preferences screen is explained below.

General - The screen in Figure 1 allows you to configure the general default operational settings.


Figure 1

Registered To:

This is the name of the Company that was entered during the registration process.

Default State:

This field is used to enter the default state. The available states are listed if you click on the down arrow. Available states are states that have a Pay Item Database. The default state is used in two places within the estimating system. First, when you enter the Pay Item Database, the initial pay item file displayed is the “default state.” Second, when you set up a new estimate, the Pay Item Database initially selected for the project is the “default state.”

Sort Tasks By:

This option allows you to change how the system will sort the tasks in the task window for each pay item. There are two sort options available:

(1) Description – The system will order the tasks in alphabetical order based on the task description
(2)

Order of Entry (Sequence No.) – The system will assign a sequence number to each task as it is entered, and the tasks will be sorted based on that number. You can also enter your own sequence numbers to sort the tasks in any order you desire.

Sort Cost Detail By:

This option allows you to change how the system will sort the cost detail within a task. The following sort options are available:

(1)

Cost Type then Description – There are five basic cost type and they will be sorted in the following order: (1) Labor, (2) Equipment, (3) Material and Supplies, (4) Sub, (5) Other, Indirects, Hauling.

(2)

Cost Type then Code (Value) – The Code is the code assigned in each of the databases for each item. For example the labor database “100” may be assigned to “Common Laborer.”

(3) Order of Entry – The items will be sorted based on the order in which they are entered.
(4)

Cost Type then Code (ASCII) - This option is different from item (2) in that the “Code” is sorted based on the character values as opposed to the numeric values. This might result in a different sort only if alphanumeric characters are used in the code as opposed to just numbers.

 

Use Alternate PI Units

Some states utilize a long unit description and require contractors to use this long unit description when submitting bids. For example instead of using our standard unit abbreviation of “C.Y” for Cubic Yard, they may require the use of “Cubic Yard.”

Load Quotes as Tasks

This option allows you to select how subcontractor and supplier prices will be loaded into an estimate. If this box is CHECKED, all prices loaded from a Pricing Sheet will be loaded as tasks, even if there are not any tasks in a pay item. If this box is NOT CHECKED, the prices will be loaded as a plug price, unless there are tasks.

Show Mark-Up as a % of Cost

The default markup percentages are displayed as a percentage of the total bid. Checking this box will change the way the system displays the mark up. See the two examples below.

Actual $

As a % of Bid As a % of Cost

Cost

$100,000.00 90.91% 100.00%
Mark-Up $10,000.00 9.09% 10.00%
Bid $110,000.00 100.00% 110.00%

Use Multiple Material Files

This option allows you to set up and maintain different material files for each state in the pay item database. By default, the system only utilizes one Master pay item database.

AutoLoad Labor

When loading equipment into an estimate, this option allows you to automatically load the operator for the equipment. Before you can use this option, you must enter the operator for each piece of equipment in the Equipment Database. See Chapter 7 – Equipment Database for more information on entering the operator.

AutoCalc Tasks

Checking this box will force the system to recalculate the tasks every time you make any changes to your estimate. Un-checking this box may help to speed up your system, especially if you have a lot of tasks. CAUTION: If this box is not checked, the tasks will only be recalculated when you press the “Recalc Project” button or whenever the system requires a project recalculation. For that reason, it is highly recommended that you check the AutoCalc Tasks button.

Mute Sounds

Checking this box will mute all the system "alert" sounds and beeps.

Reset Screens

If some of your estimate screens are not displaying properly, you can press this button to attempt to correct the problem. If the problem persists, please contact Oman Systems.

SAVE or CANCEL

Pressing the SAVE button will save the current settings and close the window. Pressing the CANCEL button will close the window WITHOUT saving any of the settings, or changes, that you may have made.


 

See also

Backup Tab
Program Paths Tab
User Information Tab
Print/Export Tab
Email Tab
Project Tab