Production Worksheet
|
Overview: This button, available from the Main Estimate view(Figure 1) allows you to see a list of all the tasks for the entire project. You can and easily change or update the production rates for all project tasks..

Figure 1
|
|
Task Quantity
|
Changing the quantity will automatically update the crew hours and the MH/Unit. |
|
Crew Prod
|
This is the production rate based on the production type. Any of the numbers in BLUE can be changed.
|
|
Prod Type
|
Double click the production type field to display the list box (Figure 2). This allows you to change the type of production used for the current task.
|
|

Figure 2
|
|
Days/Hours
|
Changes the total days (or hours) for the task. Changing the days (or hours) will automatically change the production rate for the task.
|
|
MH/Unit
|
Changes the ManHours/Unit for the task. If you change the MH/Unit, the total hours and production rate will also be changed.
|
|
|
When you close the task production worksheet, you will see the following prompt (Figure 3). Answer Yes to save any changes.

Figure 3
|